摘要:2021上半年系統(tǒng)集成項目管理工程師上午考試已結(jié)束,希賽小編為大家整理了2021上半年系統(tǒng)集成項目管理工程師上午真題及答案解析(71-75)。
為方便廣大考生考后估分對答案,希賽網(wǎng)特向廣大學員和網(wǎng)友搜集整理了相關(guān)真題信息,供大家參考。收集完整2021年上半年軟考系統(tǒng)集成項目管理工程師真題答案后,希賽網(wǎng)的老師也將在考后第一時間進行真題答案解析,敬請廣大考友考后積極關(guān)注。
現(xiàn)在要推薦給大家的是文字版2021年上半年軟考系統(tǒng)集成項目管理工程師考試上午真題及答案解析71-75題。
71、The ETL tochnology is mainly ued in (71) stage.
A. data collection
B. data storage
C. data management
D.data analysis
72、(72) is not used on perception layer of Internet of Things.
A. WLAN
B. RFID
C. Bluetooth
D.SOA
73、The (73) is a hierarchical docomposition of the total scope
of work to be carried out by the project team to accomplish the project ob jectives
and create the requirod deliverable.
A.0BS
B. WBS
C. RBS
D. RAM
74、(74) is a measure of schedule performance expreessed as the difference between the earned value and the planned value.
A. Schedule varlance (SV)
B. Cost varlance (CV)
C. Actual cost (AC)
D. Earned value (EV)
75、(75): information is not disclosed to unauthorized
indivi duals.
A. Authenticity
B. Integrity
C. Availability
D. Confidentiality
2021上半年系統(tǒng)集成項目管理工程師上午真題及答案解析【完整版】請大家點擊下載附件查看,或-掃碼-看答案,提前估分!
軟考備考資料免費領(lǐng)取
去領(lǐng)取